Dependencies


Usted está aquí: InLoox Project management glossary Dependencies

Logische Abhängigkeit von Vorgängen

Dependencies describe the relationship between two or more sequential activities. These relationships determine in which order the project team needs to complete the activities. Thus, the project manager needs to identify the dependencies between activities in order to draw up the project schedule.

There are four types of dependencies:

  1. End to start: Activity B can’t start until activity A is finished
  2. Start to start: Activity B can only start if activity A has already started
  3. End to end: Activity B can only finish if activity A has finished
  4. Start to end: Activity B can’t finish until activity A starts

These dependencies are often visualized in a critical path

Sie wollen regelmäßig Infos zum Thema Projektmanagement erhalten?


Projektmanagement-Newsletter

Erfahren Sie mehr rund ums Projektmanagement auf unserem Blog


Zum InLoox Blog

Unsere Projektmanagement-Software InLoox hilft Ihnen, Projekte schneller, effizienter und sicherer zum Erfolg zu führen


Mehr erfahren

Weitere Begriffe